Street and Sidewalk Restoration Schedule

In Construction Water

After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.

We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.

Percentage completion on this project refers to the total number of sites addressed as part of this construction contract and does not reference to the total number of PWSA restoration sites completed over time.

Progress & Status

5%
Construction Complete

Street and sidewalk restoration locations for May 10th are as follows: 

  • 1758 Bentley Drive
  • 385 Champions Drive
  • Harold Street at Zero Way
  • 3346 Webster Avenue
  • 3460 Webster Avenue
  • 3486 Webster Avenue
  • 3512 Webster Avenue
  • 3364 Milwaukee Street
  • 703 Finland at
  • 719 Finland Street
  • 741 Finland Street
  • 717 Finland Street
  • 3544 Camp Street
  • 811 Bryn Mawr Road
  • 3485 Milwaukee Street
  • 633 Kirkpatrick Street
  • 617 Kirkpatrick Street
  • 402 LaPlace Street
  • 2206 Bedford Avenue
  • Memory Lane
  • 2101 Webster Lane Way
  • Trent Street at Ishar Way
  • 504 Junilla Street
  • 2621 Elba Street
  • 635 Hollace Street
  • Wandless Street at Orbin Street
  • 848 Herron Avenue
  • 3486 Webster Avenue
  • Kirkpatrick Street at LaPlace Street
  • 402 LaPlace
  • 2206 Bedford Avenue

 

 

work is weather-dependent and subject to change

Locations & Schedule

Location Details:
Throughout service area

Start Date: Ongoing

Completion Date: Ongoing

Work Schedule: 7:00 am - 5:00 pm, M-F

Traffic Patterns: Street closures and no parking may be necessary to complete paving work.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin

mmclaughlin@pgh2o.com